SPEEDWAY

We plan to realize four pieces of speedway in the Special Economic Zone in Togo:
⦁ Speedway from Aneho over Vogan to Anfoin
⦁ Speedway from Boko in the North to Assoukope in The South
⦁ Speedway from Zalive in direction of Badougbe
⦁ Speedway from Genesis City in direction of Wogba
In total the speedway is 37 km long and 16 m wide. The speedway will have 34 connections with other streets and 44 viaducts.

Estimated costs:

Realization of the 16m-speedway 37,000 lm 23,680,000 €
Realization of the speedway connections 34 units 11,424,000 €
Realization of the speedway viaducts 44 units 12,672,000 €
Realization of the speedway bridges 640 lm 15,360,000 €
Estimated total costs for the speedway 63,136,000 €